FCCU Repair

Louisiana

Highlights

  • 274,530 Man Hours
  • Zero Lost Time Accidents
  • Completed On Schedule
  • Completed On Budget

Project Overview

The Wyatt Project Team moved on-site early and began the detailed constructability planning and scheduling. Selection of the head replacement method and cyclone replacement method along with detailed planning enabled Wyatt to schedule a significant scope to be completed Pre-Turnaround.

Wyatt engineered and fabricated the new Regenerator Head as well as two primary support structures, head/plenum/cyclone assembly an additional support structure to receive the old head after it was removed. Wyatt has performed numerous FCCU heavy lifts and drew upon this experience to assure the flawless execution of the work. Additional work was identified during the turnaround. The Wyatt team responded with the extra manpower and materials to complete the work on schedule.

Project Scope

  • Reactor and Regenerator Pre-Fabrication
  • Removal and Installation of Regenerator and Reactor
  • Replacement of 3rd and 4th stage Separator
  • Removal and Installation of Overhead Lines
  • Removal and Installation of Expansion Joint
  • Removal and Installation of Major Piping

Back to Projects

Join the Wyatt Team

We are always looking for talented people with the skills to get the job done. Apply Online

Upcoming Projects

NOW HIRING: Wyatt Field Service has immediate openings for experienced Project Managers. Contact Wyatt Human Resources Depatment at careers@wyattfieldservice.com