Coker Drum Replacement

Deer Park, TX

Highlights

  • 274,534 Man Hours
  • Zero OSHA Recordable
  • Completed On Schedule
  • Completed On Budget
  • Recognized for Outstanding Safety & Quality

Project Overview

This project involved derrick removal on two separate Coker units. The Derricks and drums were removed through precise engineering methods. Wyatt’s Engineering department includes a full-time rigging engineering group to develop specialized applications for heavy lift plans, spreader beam systems and rigging plans.

Later the new drums were installed followed by the Derricks. Wyatt planned and scheduled all of the capital and maintenance work required to accomplish the coke drum replacement within the refinery. Combine Wyatt’s rigging expertise with it’s Quality Control Program, welding technology, safety program and project management personnel and Wyatt has the total resources to complete projects safely and successfully.

Project Scope

  • Plan and Schedule all work
  • Develop Rigging Plan
  • Remove Derrick Structures on one major lift
  • Remove and install new coke drums

Back to Projects

Join the Wyatt Team

We are always looking for talented people with the skills to get the job done. Apply Online

Upcoming Projects

NOW HIRING: Wyatt Field Service has immediate openings for experienced Project Managers. Contact Wyatt Human Resources Depatment at careers@wyattfieldservice.com